Restoring a listed building in Istanbul: permits and time

Published: Up to date4 min readStonehills Real EstateReviewed by: Stonehills Real Estate

Short answer

Restoring a listed building in Istanbul needs survey, restitution and restoration projects approved by the regional conservation board, then a municipal permit. As of October 2026 the official deadlines alone add up to months: up to 30 days for the administration's zoning check under the regulation, and, in the service standards a regional board directorate publishes on the Ministry's website, 60 days for the board's project review and 30 days for its occupancy opinion. Project preparation, revisions and construction come on top. In Fatih, simple repairs such as painting or re-laying roof tiles are approved by the municipality's KUDEB office instead.

Which permits does a listed building need?

Work on a listed (tescilli) building falls into two groups:

  • Simple repairs: painting, plaster, gutters, joinery, installations and roof repairs such as re-laying tiles, which do not touch the structure. These go through a KUDEB (conservation, implementation and supervision office) repair permit instead of a building permit.
  • Major repair (restoration): everything else, based on survey, restitution and restoration projects prepared on scientific principles. These need the approval of the regional conservation board.

Fatih Municipality runs its own KUDEB office, which handles simple repairs in the district. This guide covers the second route, the board-approved restoration. For what buying in a listed area means in general, see our guide to buying a home in Istanbul's Historic Peninsula.

Three projects: survey, restitution, restoration

  1. Survey (rölöve): the building as it stands today, measured and documented with drawings, photos and a technical report.
  2. Restitution (restitüsyon): the building's original state, reconstructed from archive documents, old photos and traces on site.
  3. Restoration (restorasyon): the works project showing what is kept, what is repaired and with which methods and materials.

Board approval is not a building permit. After approval, the owner still gets the municipal permit and the works are carried out under supervision.

How long does restoring a listed building in Istanbul take?

There is no official "total time"; each step has its own service standard. We could not find the published table of the Istanbul board that covers Fatih. The board deadlines below come from the service standards of one regional board directorate (Edirne) on the Ministry's website; the municipal deadlines come from Fatih Municipality's table and a 2014 regulation amendment (October 2026):

Step Who Official deadline
Determining the protection group Regional board directorate 30 days
Preparing survey, restitution and restoration projects Architect chosen by the owner No official deadline
Zoning check of the projects Relevant administration (municipality) 30 days
Board review of the projects Regional conservation board 60 days
Architectural project approval Fatih Municipality 15 days plus external processes
Building permit Fatih Municipality 35 days
Works Contractor, under supervision Depends on the job
Board opinion for the occupancy permit Regional conservation board 30 days

Adding the 30-day zoning check, the 60-day board review, the 15-day project approval, the 35-day permit and the 30-day occupancy opinion gives about 170 days of official waiting time alone if each step runs after the previous one, as of October 2026; the municipality's project approval and permit steps may partly overlap. That excludes project preparation, revision requests and construction, and the deadlines apply to complete files.

Fatih also has an older data point. In a CNN Türk report from January 2017, the then mayor of Fatih, speaking about projects on plots next to listed buildings, said a project used to take "at least 3 years" to come out of the board. The same report says projects on unlisted plots and plots next to listed buildings were handed to the municipality's KUDEB, while listed buildings stayed with the board. We found no current official figure for today's waiting time.

What slows a restoration down?

  • No protection group: a listed building whose protection group has not been set may first need a board decision on its group.
  • Missing documents: board applications ask for photos, site plans, zoning status and the municipality's preliminary approval; Fatih issues the drawn zoning status in 1 day, with extra steps if a KUDEB decision is needed.
  • Shared ownership: applications need a current ownership document, and co-owners who disagree can stop the process before it starts. See our guide to shared title deeds.

Who pays for it?

The owner pays, but the Ministry of Culture and Tourism offers repair aid. Under the Regulation on Aid to Immovable Cultural Property, privately owned listed buildings can get project aid and works aid. Works aid can cover up to 70 percent of the estimated cost for individual applications and 80 percent for collective ones, within a cap. From 1 February 2025 the caps were TL 1,132,266 for project aid and TL 4,529,078 for works aid. Communiqué 2026/2, published in the Official Gazette of 30 January 2026 (No. 33153), updated them again from 1 February 2026; we could not verify the 2026 amounts, so check them in the communiqué's annex or with the Istanbul Provincial Culture and Tourism Directorate. Aid is also limited by the year's budget.

Where to start in Fatih

  1. Check the title deed for a listing annotation and ask the board directorate for the protection group.
  2. Get the drawn zoning status from Fatih Municipality.
  3. Hire an architect with board experience to start the survey.
  4. If you want state aid, learn the application calendar before the project starts.

In areas with many listed buildings, such as Balat and Fener, factor this timetable into the price you offer. This guide is general information; for a specific project ask a restoration architect, and for a refusal or appeal ask a lawyer.

Frequently Asked Questions

Can a foreigner apply for restoration permits on a listed house they own in Istanbul?

Yes. The permit and aid rules are tied to the property and its owner, not to nationality: the regulation on repair aid speaks of privately owned listed property and individual applications go to the provincial culture and tourism directorate. In practice the drawings, applications and board decisions are all in Turkish, so a foreign owner usually works through a restoration architect and, for documents signed on their behalf, a notarised power of attorney.

When do I have to apply for the Ministry's repair aid?

By the deadline the aid commission sets each year. Under the aid regulation (consolidated text, last amended in May 2023), individual applications go to the provincial culture and tourism directorate by that yearly deadline, while collective applications, made together with the municipality for a street or group of buildings, are forwarded by the end of May. A building that already received aid for the same work cannot apply again until 10 years after the last payment, except for force majeure or disaster damage. Ask the Istanbul directorate for the current calendar before the project starts.

How long does a tax exemption request take after restoration?

Up to 30 days at the board directorate, according to the service standards one regional board directorate (Edirne) publishes on the Ministry's website in 2026. The Istanbul boards' own table may differ, so ask the board that covers Fatih when you file, and keep the approved project and completion documents ready.

Sources

  1. Ministry of Culture and Tourism, Conservation Boards: public service standards, Edirne Regional Board Directorate (Turkish) · 21 October 2026
  2. Fatih Municipality, Zoning and Urban Planning Directorate service standards table (Turkish) · 21 October 2026
  3. Alomaliye, Amendment to the Regulation on Building Principles and Supervision of Immovable Cultural Property (Official Gazette 7 Dec 2014, No. 29198) (Turkish) · 21 October 2026
  4. Regulation on Aid to Immovable Cultural Property (Lexpera consolidated text) (Turkish) · 21 October 2026
  5. Alomaliye, 2026 monetary limits for aid to immovable cultural property (Communiqué 2026/2), 30 January 2026 (Turkish) · 21 October 2026
  6. Benguturk, Project and works aid amounts for immovable cultural property updated, 30 January 2025 (Turkish) · 21 October 2026
  7. Anadolu Agency, Project and works aid amounts for immovable cultural property updated, 30 January 2025 (Turkish) · 21 October 2026
  8. Regulation on Building Principles and Supervision of Immovable Cultural Property, consolidated text on the Ministry's conservation boards website: definitions of minor repair and major repair (Turkish) · 21 October 2026
  9. Karar, Tarihi Yarımada'da 'tarihi yetki' belediyeye verildi, 25 December 2016 (Turkish) · 21 October 2026
  10. CNN Türk, 'Tarihi yetki' belediyeye verildi, 4 January 2017 (Turkish) · 21 October 2026

The information on this page is for general guidance only and does not constitute legal, tax or investment advice. Figures relate to the source and date stated.